
Location
Dalrymple Bay Coal Terminal
Duration
18 Days
Current Status
Completed
Completion
Nov 2019
Scope of Work
Shutdown + Commissioning
Contract Type
SOR's
HSE
No incidents - Zero Harm
Client Referees
Available on Request

Resources + Key People
Project Manager: Brian Lynch
Project Superintendent: Marc Richards
Technical Advisor: Dick Jones
Project Engineer: Brad Klease
Site Supervisors: Ken Smith, Gregg Schneider, Paul Mare
Project Description
SLE Services was contracted by DBCT P/L to undertake a planned shutdown on SR5 to remove and replace the slew bearing on the machine involving the following work:
Electrical HV and control cable removal and reinstallation
Set up of jacking haunches for jacking of machine
Jacking of machine with 4 x 400t mechanically locked jacks
Replacement of slew bearing with new free issued item
Overhaul of slew drives
Blast & paint & scaffolding services
Structural modifications
All work was completed in full, on time and to budget with no incidents for the entire shutdown. SLE managed several different contractors on various work fronts and excellence in quality & safety was achieved on all fronts.
Project Execution
The complete shutdown was executed in full and without any incidents. Our core crew that is very experienced in large scale and complex shutdowns were utilised on a 3 panel roster over the 18 day duration. SLE’s 4 x 400t synchronous jacking system was utilised for the jacking of the machine for removal and replacement of the slew bearing.
Time Constraints, Challenges + Innovations
SLE’s EVO system managed a very safe and controlled lift of the upper slew deck and was able to provide centre of gravity determination to assist in determining the optimum centre of gravity position of the machine and subsequent trimming mass applied to the machine for optimal future bearing life.
Lessons Learned
Early engagement of all personnel through our Recruitment team proved to be a key to success for SLE in onboarding for site.
#casestudy #projectsheet #dalrymplebaycoalterminal